Dealer Project Kit Planning & Quoting Guide | Simply Controlled

Use this practical workflow to turn a project brief into an accurate parts takeoff, a defensible quote and a predictable purchasing list. Simply Controlled dealer project kits are preconfigured, single-brand Shopify products that contain specific component SKUs and quantities. They help reduce ordering friction; they do not replace site design, installation requirements or professional judgement.

Browse all dealer project kits | Dealer Workbench | Quick Order

1. Define the installation before choosing a kit

Record the application, jobsite location, expected quantities, customer priorities and installation constraints. For an ERV, that means calculated airflow, duct access and control placement. For downlights, identify fixture type, ceiling pitch, trim finish, colour temperature, dimming requirements and exact fixture count. For water protection, document credible leak locations and the existing shutoff arrangement.

2. Match the application to a project kit family

3. Reconcile the bill of materials (BOM)

Open the individual kit product page and copy the exact component SKUs and included quantities into your estimate. Do not assume that a photo represents every accessory. Check the intended colour, voltage, trim size, controller version and any model-specific options.

Example kit Included model reference Additional design checks
Panasonic Elite Plus 150 + control 1 × FV-15ESC1; 1 × FV-SCVE2 Airflow sizing, duct layout, exhaust/supply termination and commissioning.
Lotus adjustable white gimbal 8-pack 8 × LRG3-5CCT-HO-WH Ceiling cutout, finish, aiming, controls and total fixture count.
EcoNet six-sensor shutoff 1 × EVC400-MW-SK6; 1 × BB3K Valve compatibility, sensor placement and backup power.
Comtrend four-remote PoE 1 × PG-9182PT; 4 × PG-9182PoE Electrical circuit topology, outlets and site link performance.

4. Separate what is included from what must be quoted separately

A kit is not automatically a turnkey installed system. Depending on the application, separate line items might include ducting, exterior terminations, insulation, wiring, mounting/channel hardware, junction boxes, circuit protection, compatible dimmers, external amplification, network configuration, labour, testing and commissioning. Only count an accessory as included when its precise model and quantity appear on that kit's current product page.

5. Check the economics and dealer terms before committing

Use the price available to the authorized dealer account, verify real stock and purchasing restrictions, and consider shipping, returns, taxes and manufacturer support. Do not assume that kit pricing guarantees a discount against independently priced components. Any separate promotion is conditional and subject to its own dates, eligibility and combination rules. Quote material and installation labour as distinct decisions.

6. Confirm fulfillment and installation readiness

  1. Reopen each component specification and validate installation requirements and current firmware/controls where relevant.
  2. Confirm availability and identify any backorders or possible substitutions before providing a committed delivery date.
  3. Check the project BOM against the number of rooms/locations and build a punch list for omitted accessories.
  4. Document any commissioning, network or programming work that occurs after installation.
  5. Save the kit's SC- SKU, the individual component model numbers and relevant instructions with the customer quotation.

When should you choose individual components instead?

Order individually when the kit's quantities, colours, controls, fit, electrical characteristics or site requirements do not match the project, or when a separately approved alternative makes more commercial sense. Bundles are convenience tools—not permission to substitute or mix unspecified model variants.

Further professional guidance

Need a project-specific specification review? Contact Simply Controlled through the existing dealer service channels with the intended system, preferred SKUs and the critical site details.